Total Cost
83.8 Lakh

Grey Structure Material Cost
37.24 Lakh

Finishing Material Cost 38.55 Lakh

Labour Cost 8.02 Lakh

Price Per Sq Ft 5,173

[ays_chart id=”2″]

includes materials for the basic house structure including foundation, floors, walls, roofing, and plastering.

ITEMRATEQUANTITYCOST
Bricks + Rorhi26/Unit450101,170,260
Cement1328/Bag484642,752
Sand85/Cft.2420205,700
Crush138/Cft.1377190,026
ITEMRATEQUANTITYCOST
Roof Insulation249/Sft.11729,133
Termite Proofing1700/Liter46,800
Water Proofing114/Sft.11713,338
ITEMRATEQUANTITYCOST
Excavation & Backfill + Ghassu23/Cft.295768,011
Steel Reinforcement264600/Tonne3793,800
ITEMRATEQTYCOST
Power Sockets1475/Socket1217,700
Fan Dimmer1250/Dimmer810,000
Universal Switch Socket625/Socket2415,000
Telephone Sockets (RJ-11)595/Socket21,190
Distribution Board110741/Unit1110,741
TV Sockets495/Socket52,475
Switch Boards1390/Board2433,360
ITEMRATEQTYCOST
Power Sockets1475/Socket1217,700
Fan Dimmer1250/Dimmer810,000
Universal Switch Socket625/Socket2415,000
Telephone Sockets (RJ-11)595/Socket21,190
Distribution Board110741/Unit1110,741
TV Sockets495/Socket52,475
Switch Boards1390/Board2433,360
ITEMRATEQTYCOST
3/4” dia. Electrical PVC Conduit with accessories30/Rft.81024,300
1” dia. Electrical PVC Conduit with accessories31/Rft.2437,533
1.5” dia. Electrical PVC Conduit with accessories41/Rft.281,148
2” dia. Electrical PVC Conduit with accessories50/Rft.321,600
PVC Ceiling Fan Hook550/Unit126,600
ITEMRATEQTYCOST
1.5mm Sq. (3/.029) PVC insulated Cu.conductor wire (Light point wiring)4944/Coil839,552
2.5mm Sq. (7/.029)PVC insulated Cu. conductor wire “Circuit wiring (Normal & UPS) & sockets Split AC7931/Coil863,448
4mm Sq. PVC insulated Cu. Conductor wire (Power Sockets wiring) Split AC12360/Coil449,440
Four core 16 mm Sq. PVC insulated Cu. conductor cable (From DB-GF to wapda Energy Meter)1494/Rft.70104,580
Cat 5 for Telephone Cable376/Rft.4115,416
TV Coaxial Cable for TV cable357/Rft.12243,554
Porch Lights1692/Light46,768
Bedroom Lights1330/Light1215,960
Bathroom Lights1330/Light810,640
Open Area Lights1330/Light810,640
Kitchen Lights3500/Light828,000
Stair Case Lights1400/Light68,400
Drawing Room Lights3928/Light415,712
Living Area Lights3928/Light831,424
Ceiling Fans9500/Fan876,000
Exhaust Fans5000/Fan630,000
ITEMRATEQTYCOST
Staircase and Terrace Railing1605/Rft.3657,780
Main Gate132500/Unit1132,500
TEMRATEQTYCOST
Water Closet21696/Unit486,784
Vanity Basin13575/Basin454,300
Basin Mixer12200/Mixer448,800
Muslim Shower2830/Unit411,320
Shower Set36160/Unit4144,640
Toilet Paper Holder1356/Unit45,424
Beveled Edge Mirror7040/Mirror428,160
Soap Dish1083/Dish66,498
ITEMRATEQTYCOST
Geyser32500/Unit132,500
Manhole5445/Unit15,445

Plumbing works include underground piping and drainage systems materials.

ITEMRATEQTYCOST
25 mm o/d Pipe107/Rft.16217,334
32 mm o/d Pipe175/Rft.6511,375
40 mm o/d Pipe268/Rft.164,288
50 mm o/d Pipe402/Rft.208,040
ITEMRATEQTYCOST
2″ Dia. Pipe260/Rft.6516,900
3″ Dia. Pipe350/Rft.6522,750
4″ Dia. Pipe170/Rft.9716,490
ITEMRATEQTYCOST
32 mm o/d452/Rft.2410,848
50 mm o/d615/Rft.159,225
ITEMRATEQTYCOST
GI Welded Pipeline 3/4” i/d416/Rft.12250,752
Gas Cock 3/4″ i/d1335/Unit22,670
ITEMRATEQTYCOST
Booster Pump 0.75 HP155000/Unit1155,000
Submersible Water Transfer Pump 1 HP145500/Unit1145,500
Floor Drains1710/Unit610,260
ITEMRATEQTYCOST
1″ dia Class “E”110/Rft.10911,990

Wood, Metal & Tile Works include cabinets, wardrobes, flooring, and all aluminum and iron works.

ITEMRATEQTYCOST
False Ceiling130/Sft.48663,180
Paint57/Sft.6885392,445
ITEMRATEQTYCOST
Floor Tiles310/Sft.1712530,720
Floor Skirting271/Sft.598162,058
Ceramic Tiles on Walls & Dado289/Sft.608175,712
ITEMRATEQTYCOST
Main Entrance Door101701/Door1101,701
Room Doors38420/Door4153,680
Washroom and Other Doors27120/Door6162,720
Roof and Terrace Doors27120/Door381,360
ITEMRATEQTYCOST
Aluminium Room Windows20340/Window6122,040
Aluminium Bathroom Windows13560/Window454,240

[ays_chart id=”2″]

Foundation & Structure

Foundation & Structure includes materials for the basic house structure including foundation, floors, walls, roofing, and plastering.   37.76 Lakh

Bricks + Rorhi

26/Unit

45010
Total Cost

11.7 Lakh

PKR 1,170,260

Cement

1328/Bag

484
Total Cost

6.43 Lakh

PKR 642,752

Sand

85/Cft.

2420
Total Cost

2.06 Lakh

PKR 205,700

Crush

138/Cft.

1377
Total Cost

1.9 Lakh

PKR 190,026

Roof Insulation

249/Sft.

117
Total Cost

29.13 Thousand

PKR 29,133

Termite Proofing

1700/Liter

4
Total Cost

6.8 Thousand

PKR 6,800

Water Proofing

114/Sft.

117
Total Cost

13.34 Thousand

PKR 13,338

Excavation & Backfill + Ghassu

23/Cft.

2957
Total Cost

68.01 Thousand

PKR 68,011

Steel Reinforcement

264600/Tonne

3
Total Cost

7.94 Lakh

PKR 793,800

Total: Labor Cost

6.56 Lakh